Beskrivelse: Omexom has been awarded by Hafslund Nett to upgrade the Ulven substation in Oslo, addressing increasing short-circuit levels and enhancing safety and efficiency. Les mer ↧
Kategori
Rehabilitering
Infrastruktur
Elektrisk infrastruktur
Verdi og størrelse
Miljøsertifiseringer
Ingen registrerte
Hva skal bygges?
Switch fields |
14 fields |
Capacitor battery switches |
3 switches |
Non-operational switching fields dismantling |
6 fields |
Aktører
Arkitekt
Rådgivende ingeniør
Underentreprenør
Klikk på aktørene for å se kontakter
Siste utvikling: Omexom has been awarded the contract by Hafslund Nett to upgrade the Ulven substation in central Oslo. The project has just started.
Neste steg: Completion of the Ulven substation upgrade is scheduled for November 2020. Specific tasks include upgrading the 47 kV system, changing switches, dismantling non-operational systems, and adapting the control system. Statnett will also carry out their own work on some plant fields.
Fase: Ferdig bygd